On July 31, He Rong, the first-level inspector of the Guangdong Provincial Department of Industry and Information Technology, and a group of four people came to Shantou to investigate and supervise the pollution control and other work in the Lianjiang River Basin.
The supervision team inspected the construction of printing and dyeing centers in Chaoyang District and Chaonan District and the production site of Shantou Jiamei Knitting Co., Ltd., and listened to reports on the construction progress of the two printing and dyeing centers and the use of special funds. Then he went to the project department of Guangdong Yudean Shantou LNG Receiving Station to investigate and understand the progress of the project and the problems that need to be solved through coordination.
Chaoyang and Chaonan printing and dyeing Park situation
At present, the water supply project and electricity supply of Chaoyang Printing and Dyeing Center The construction of production facilities such as engineering, gas engineering, heating engineering, and sewage treatment, as well as the construction of park roads, employee dormitories, management centers, general workshops, gas engineering, communication engineering and other supporting facilities are basically completed, and the conditions for printing and dyeing enterprises to enter the park and start production are met; 16 companies All large-scale self-built factory enterprises have entered the park for construction, some have been completed and put into production, and other enterprises are speeding up construction; 16 small enterprises have settled in general factories and are designing and installing equipment.
Chaonan Printing and Dyeing Center has completed the construction of PPP environmental infrastructure project. The first phase of the sewage treatment plant was completed and put into operation. The phase 1 sewage treatment plant has completed the main project before the end of April 2020, entered the equipment commissioning stage, and is ready to accept corporate water treatment; the cogeneration project was successfully connected to the grid on May 27, 2020, fully realizing steam, compressed air, electricity Secure supply of three main products.
All general-purpose factories have been handed over to settled enterprises, and 50 self-built factory enterprises have all entered the park for construction. The official trial will be held at the end of June. There are 24 enterprises put into production, including 18 general-purpose factories and 6 self-built factories; it is expected that the number of enterprises that will be officially put into trial production before the end of the year will reach 60.
He Rong affirmed the progress of Chaoyang District and Chaonan District in promoting the project construction. Chaoyang and Chaonan districts are required to standardize arrangements and accelerate the use of special funds, and continuously improve the supporting construction of the park. It is necessary to increase policy support for technological transformation, guide and serve printing and dyeing enterprises to enter the park, promote more printing and dyeing enterprises to trial production as soon as possible, and expand the park economy. It is necessary to standardize park management and strive to create a green and environmentally friendly demonstration park. </p